Stop production for 60 days! Several chemical enterprises plan to overhaul
Meda since January 21, some polymerization production lines in Jiangmen production base have been stopped for maintenance. It is preliminarily estimated that the maintenance time for this shutdown is about 60 days. It is estimated to reduce the yield of nylon 6 slices by about 25,000 tons, and that the yield of nylon 6 fibers is expected to decrease by about 11.000 tons.
According to Yisheng Dahua news, yisheng Ningbo2 million tons of PTA will be overhauled for 2 weeks on February 10, and 2.25 million tons of ptaof Yisheng Dahua will be overhauled on March 1.
Yangzi Petrochemical the 490,000 tons/year pure benzene plant will carry out a 55-day overhaul plan until the middle of March.
Maoming Petrochemical Company1# high pressure polyethylene, full density polyethylene, SBS rubber, 1# ethylene glycol and 1# styrene are planned to be put into production on March 15 in cooperation with the new production capacity and will be stopped on February 25.
Zhejiang Petrochemical Company the 600,000 tons/year styrene plant is scheduled to be stopped for overhaul in the middle of this month, and the overhaul time is about 20 days;
message jiaxi, Anhui the styrene plant of 350,000 tons/year has been stopped and maintenance has begun.
Changzhou new day the 300,000-ton styrene plant was gradually stopped from January 24 and was overhauled for 30 days. In February, there were maintenance plans for 600,000 tons of Zhejiang Petrochemical Company, 350,000 tons of Anhui Jiaxi company and 100,000 tons of Maoming Petrochemical Company.
Hebi, Henan, zhongxin at the end of January, methanol was stopped for overhaul. Lunan Guohong fulfilled the overhaul for 7-10 days on February 8. Phoenix had a negative expectation, and Xuyang, Hebei province, had a negative operation.
Shandong yancon640,000 tons/year methanol plant parking maintenance 7 days from February 8.
Shaanxi industrialization the maintenance plan of BDO unit is stored in the middle of February or the end of the month.
Xinjiang New Industry the maintenance plan of BDO unit is stored on February 25, and it is expected to be 5 days.
In addition, longRun Tea, Hite, Dong Chen chemical industry, Hualian petrochemical many domestic liquefied gas manufacturers have announced the start of maintenance, and the recovery time is to be determined. 12 refineries including Dongying petrochemical and Hualian petrochemical announced the overhaul time, involving 35.6 million tons of production capacity.
In addition to domestic chemical enterprises undergoing overhaul, overseas chemical leaders have also been frequently affected by force majeure recently, unpredictable emergencies occurred in kostron's hydrochloric acid logistics in Leverkusen., immediately announced the force majeure on the supply of HDI and IPDI; The polypropylene copolymer (PP-C) of total energy located at the factory in confreville, Paris, France occurred force majeure, and the supply or interruption of products took several weeks.
Since the end of 2021, major factories such as Dow, French total and innix have successively announced force majeure. The production of polyethylene, butanediol and other products has been affected, and the force majeure has not been lifted so far.
Dow two of the three cracking units failed, and all grades of polyethylene products produced in Dow Europe were affected by force majeure.
France total energy the PS (polystyrene) device in France officially declared force majeure.
Akoma located in France, 380,000 tons/year acrylic acid and refined acid, 120,000 tons/year butyl acrylate, and a total of about 140,000 tons/year isooctyl acrylate, methyl acrylate and ethyl acrylate force majeure.
Innix in French factories, butyraldehyde, isobutyraldehyde, n-butyl alcohol, isobutyl alcohol and ISO-octyl alcohol, of which the production of butyl alcohol and octanol are about 160,000 tons/year and 125,000 tons/year respectively.
Brazilian polymer producer Braskem the C- line polypropylene (PP) production department in Laporte, Texas was closed.
......
Raw materials open a full-line rising mode
2024 Polycarbonate PC Industry Market Event
Acrylonitrile price shocks down, when can the imbalance between supply and demand be solved?
New trends in the bisphenol A market: raw material acetone rose, downstream demand is difficult to boost
With a total investment of 1.024 billion yuan, Sinochem Dongda (Quanzhou) Polyether Polyol Signed
Epoxy resin market after the National Day, the price rise can be sustained?
Total investment 1.5 billion, Hebei Jinbang new materials 80000 tons of epoxy resin project accelerated
Quick Response
Customer service is available 24/7 for extremely fast response
Exclusive Services
Dedicated consultant 1 to 1 service
Massive Resources
Connecting resources upstream and downstream
Technology Advanced
Technology Information Service
Transaction Security
Merchant authentication and risk control model
One-stop service
Trading logistics warehouse-style services